Wood Avenue rebuild will be lengthy
By Robert Palmer - TNValleyNow.com
TimesDaily
Portions of North Wood Ave. where the street has been patched multiple times because of water, sewer line and pothole repairs.

FLORENCE — With money now in hand, city officials are working out the details of tearing up Wood Avenue and putting it back together again.

Florence received almost $4 million in federal money through a state program to rebuild the road bed and move aging utilities along almost a mile of the heavily traveled street. The city must provide a 20 percent funding match.

The project will replace and relocate underground utilities, dig up the road bed, and repave the surface. Work should begin this spring.

“The Wood Avenue work will have to be done in stages because the utilities are in the center of the street,” City Council President Dick Jordan said. His district includes the downtown and historic districts, where Wood Avenue is a major thoroughfare.

“Utilities are a significant portion of this,” said Mike Doyle, director of Water and Wastewater Department. “We’ll be cutting down the road bed and that will put it close to the utilities in the ground. This is very serious.”

The 16-inch water main is about 100 years old, and the sewer line needs to be at a deeper depth, he said.

Wood Avenue is an old thoroughfare and the road bed was never built to withstand heavy automobile traffic. As a result, aging water and sewer lines frequently break or develop leaks, requiring cuts in the pavement that make for a bumpy ride.

The work will extend from Tuscaloosa Street next to the library to just south of the Seven Points. Along the way, the street is lined with historic houses and towering oak trees. The trees are of concern to many.

“We will try to save all the trees we can,” city engineer Bill Batson said.

Doyle pointed out the right of way is narrow along the street.

Batson said new curb and gutter is included in the project, but sidewalks should not be disturbed during the work, which could take up to six months.

Residents along the street will continue to have water and sewer service from existing lines while the work is being done, Doyle said. Once the new utilities are installed, residents will be connected to the new lines, he said.

Doyle and Batson are meeting with consulting engineers and Alabama Department of Transportation officials to finalize plans.

“We want to keep as much of the street open as possible to local traffic and residents while the work is going on,” Jordan said.

Not registered? Click here
E-mail this
Print this
Comments
2 comments on this item

Who in Decatur cares about this?

Really? No one!!!!!

You must be logged in to post a comment. click here to log in.
Follow Us On Twitter 
Decatur Daily @DecaturDaily
High School Sports @DecaturPreps
Living @DecaturLiving
Seth Burkett @DD_SethBurkett
Bill Campbell @DD_BillCampbell
David Elwell @DD_DavidElwell
Deangelo McDaniel @DD_Deangelo
Eric Fleischauer @DD_Fleischauer
Briana Harris @DD_BrianaHarris
Bayne Hughes @DD_BayneHughes
Ben Montgomery @DD_BMontgomery
Cody Muzio @DD_CodyMuzio
Meredith Qualls @DailyMeredith
Mary Sell @DD_MarySell
Ronnie Thomas @DD_RonnieThomas

Alerts The Way You Want Them
Sign up for our any or all of our alert services & receive breaking local news, daily updates, sports, weather & more in your inbox or mobile device.
Mobile Devices
View our site on your smartphone or tablet devices.
Text Alerts (Subscribers Only)
Breaking news, bible quotes, weather, sports, horoscopes, stocks & more sent to your mobile devices.
Email Newsletter
Receive breaking local news, daily updates, sports, weather & more. Enter your e-mail address below.




Most Read
Most Recent
Most Commented
Events Calendar
Wednesday, Jun 19, 2013 see all events
  • Wed
  • 19
  • Thu
  • 20
  • Fri
  • 21
  • Sat
  • 22
  • Sun
  • 23
  • Mon
  • 24
  • Tue
  • 25
The Helmet Project
Carnegie Visual Arts Center
10:00 AM - 5:00 PM
Peggy Towns Speaks at Decatur Public Library
Decatur Public Library
6:30 PM
The Helmet Project
Carnegie Visual Arts Center
10:00 AM - 5:00 PM
The Helmet Project
Carnegie Visual Arts Center
10:00 AM - 5:00 PM
The Helmet Project
Carnegie Visual Arts Center
10:00 AM - 5:00 PM
Madison City Farmers Market
Madison City Farmers Market Lot
8:00 AM - 1:00 PM
CAMP PRINCESS 2013: FOLK MUSIC
Princess Theatre
9:00 AM - 12:00 PM
CAMP PRINCESS 2013: FOLK MUSIC
Princess Theatre
9:00 AM - 12:00 PM
The Helmet Project
Carnegie Visual Arts Center
10:00 AM - 5:00 PM
Poll
Should Decatur build one, two or no new high schools?